Data centers would need council permits and stay in business park and industrial zones under rule up Thursday

A code change before the Planning and Zoning Commission Oct. 15 would define data centers as buildings over 5,000 square feet and allow them only as conditional uses in four districts; drive-thru queue rules are also being rewritten.

Reese Fenn

October 12, 20262 min read

College Station would add data centers to its development code as a defined use under a change the Planning and Zoning Commission takes up Thursday, and only in four business and industrial zoning districts with a council-approved permit.

The commission meets at 6 p.m. Thursday, Oct. 15, in the City Hall council chambers, 1101 Texas Ave. Final action is slated for the Oct. 22 City Council meeting, according to the agenda, though that date is marked subject to change.

What the rule would say

City staff wrote that data centers have drawn growing attention over the past year as communities work out how to handle them in their development codes. The amendment would add a definition to the Unified Development Ordinance and a line for the use in its table of allowed uses.

Under the proposed definition, a data center is any building, part of a building or accessory building over 5,000 square feet that is used mainly for computers, servers, network equipment and related gear that collect, store, manage, process or transmit digital data.

The redlined use table marks the new use with a "C," meaning conditional, in four zoning districts: BP, BPI, M-1 Light Industrial and M-2. No district would allow one by right.

A conditional use permit gives the council discretion over each request, judged on location, design, layout and likely effects on nearby properties, the staff summary says. The council could also attach conditions on buffering, screening, lighting, noise and other concerns. Staff recommends approval.

Drive-thru lines get a rewrite too

The same agenda carries the first update since 2003 to the city's rules on how many cars a drive-thru must be able to stack off the street. Staff wrote that drive-thru designs have changed since then and that curbside pickup has absorbed some of the demand.

The redlines would:

  • Cut the minimum queue for a bank teller lane from four spaces to two, and for an oil change bay from three to two, citing lower observed demand.
  • Drop photo labs and self-service car wash stalls from the table and add pharmacies at three spaces.
  • Split restaurants into two types: a standard drive-thru with an order box, which requires four spaces at the order box and three between the box and the pickup window, and a pickup-window-only lane for orders placed ahead, which needs four.
  • State in the drive-thru section that the city's administrator may require a queuing study for high-intensity drive-thrus, a power staff says already exists elsewhere in the code.

Staff also recommends approval of that change, which likewise heads to the council Oct. 22.

Residents who want to speak must register with the commission secretary at least two hours before the meeting, online at forms.cstx.gov or by calling 979-764-3570, according to the agenda.

Sources

collegestationtx.api.civicclerk.com

collegestationtx.api.civicclerk.com

Share

Reese Fenn

Reese Fenn writes about community life, schools, public safety, and local events in College Station.

Related Stories

More in Texas