Back to College Station

TxDOT settles on roundabouts for a four-lane Harvey Road east of Associates Avenue, with an Oct. 20 open house

The state's preferred plan for 2 miles of SH 30 out to FM 158 would double the lanes, add sidewalks and bike paths, and take strips of two city parks; construction has no funding yet.

Reese Fenn

October 13, 20262 min read

The Texas Department of Transportation has picked roundabouts as the way forward for a widened Harvey Road on College Station's east side, and it will show residents the selected design at an open house next Tuesday, Oct. 20.

The SH 30 corridor plan covers about 2 miles of Harvey Road from Associates Avenue to FM 158. TxDOT's Bryan District, working with Brazos County and the City of College Station, proposes widening the road from two lanes to four, two in each direction, turning intersections into roundabouts and building new sidewalks and bicycle facilities along the route.

Three options narrowed to one

At a meeting last December, TxDOT showed three alternatives: roundabouts, a two-way center left-turn lane, and hooded left-turn lanes. The agency's hearing notice says the roundabout version is now "the selected alternative for further development." TxDOT says the plan is meant to handle future traffic growth, improve safety and lower crash rates.

Today the road has one lane each way, shoulders roughly 10 feet wide and center turn lanes only in places, with few sidewalks or bike accommodations, according to the project page. That page also states plainly: "Construction is currently not funded."

Two parks would give up land

The design would require buying right-of-way from Veterans Park and Athletic Complex at 3101 Harvey Road and from Summit Crossing Park at 3880 Alamosa Street. TxDOT says the land taken would not affect how either park functions and expects to make a "de minimis" finding under federal and state park-protection rules.

Because the parks are protected under Chapter 26 of the Texas Parks and Wildlife Code, TxDOT is pairing the open house with a recorded virtual public hearing on those park impacts. The notice also says the project may involve construction in wetlands and would involve work in a floodplain.

How to weigh in

  • In person: 5 to 7 p.m. Tuesday, Oct. 20, at the Meyer Senior & Community Center, 2275 Dartmouth St. The format is a drop-in open house with displays and staff available for questions.
  • Online: The virtual hearing, a prerecorded presentation rather than a live broadcast, goes up on TxDOT's SH 30 Corridor Plan page at 5 p.m. Oct. 20 and stays up at least 15 days.
  • Comments: by mail to TxDOT Bryan District Office, Attn: SH 30 Corridor Plan, 2591 North Earl Rudder Freeway, Bryan, TX 77803; by email to BRY_PublicComment@txdot.gov; or by voicemail at 713-263-5521 from Oct. 20 through 11:59 p.m. Nov. 4. All comments must be received or postmarked by Wednesday, Nov. 4.

Anyone needing an interpreter or a disability accommodation has to ask by 4 p.m. Wednesday, Oct. 14, by calling Bryan District public engagement specialist Steve Fullhart at 979-778-9231. Project files can be viewed by appointment at the Bryan District office; questions go to 979-778-2165.

Sources

TxDOT

ftp.dot.state.tx.us

TxDOT

collegestationtx.api.civicclerk.com

Share

Reese Fenn

Reese Fenn writes about community life, schools, public safety, and local events in College Station.

Related Stories

More in Texas