College Station ISD trustees are scheduled Tuesday to consider a $25,392,035 guaranteed maximum price for construction of a new Central Office and renovations to the existing administrative building, according to a Sept. 14 district board preview.
The College Station ISD Board of Trustees will meet for a workshop at 5 p.m. and a regular meeting at 7 p.m. Sept. 15 in the CSISD Boardroom at 1812 Welsh Ave. Both sessions will be livestreamed on the district’s YouTube channel, College Station ISD said.
What is on the table
In its “Before the Board” preview posted Sept. 14, College Station ISD said trustees will discuss and consider the proposed Guaranteed Maximum Price, or GMP, for the Central Office project. The figure of $25,392,035 is $7,965 below the project’s $25.4 million construction budget, the district said, and followed an Aug. 19 bid process.
If the board approves the GMP, College Station ISD said construction is scheduled for completion in December 2027. Renovations to the existing Central Office are expected to finish in July 2028, before students return for the 2028-29 school year.
How the project evolved
The 2023 bond package included Proposition A funding to purchase and renovate an existing building for a new Central Office, along with renovations to the current facility, according to College Station ISD. After evaluating multiple existing buildings, district-owned property, project feasibility and budget considerations, the district reconvened the 2023 bond steering committee and determined that new construction was the best path forward, the preview said.