A storm sewer job on Southwest Parkway needs another $73,392 after crews found that a 12-inch waterline in the way would take more digging, and more valves, to lower than planned. The College Station City Council takes up the change order Monday on its consent agenda.
The project replaces about 500 feet of storm sewer along the parkway, including a culvert crossing, plus pavement repair and traffic control.
According to the staff summary, potholing to check whether the waterline conflicted with the new pipe showed that dropping the line would require removing and replacing more of it, along with extra valves so a neighboring apartment complex and businesses keep service during construction. Staff brought the change to the council separately so the job's construction contingency stays intact once work starts.
The project has an $850,000 budget in the streets capital fund. The city has spent or committed $663,699, which leaves $186,301 for this contract and later costs. Larry Young Paving holds the construction contract.