The company behind Savannah Oaks has laid out its first timeline for the south College Station project, saying infrastructure work could begin in early 2027 and the first residents could move in by early summer 2028.
Silverfin Land Development LLC released the details in an announcement WTAW posted late Sunday, three days after the City Council unanimously approved the zoning for the 1,266-acre site off State Highway 6 between Pebble Creek and Southern Pointe. Silverfin, which is based in Corpus Christi, calls it the biggest planned development the city has seen.
How many homes
The planning packet the council reviewed set density limits but did not give a total number of homes. Silverfin now says its current plan calls for roughly 2,688 single-family homesites, along with two townhouse sites covering about 25 acres and possible multifamily housing.
The company said the final lot count still depends on later planning, infrastructure and subdivision approvals, and that the zoning's allowance of as many as eight lots an acre in some areas is a ceiling, not its proposed count.
Schedule
Silverfin said Phase 1 infrastructure is expected to start between January and March 2027, depending on final engineering, permits and market conditions. It said it expects to name the homebuilders soon and is aiming to open model homes and welcome its first residents in early summer 2028. A traffic study in the city's packet assumed full buildout by 2039.